Manage your waste more responsibly
Companies attempting to dump over-sized or hazardous items at the Energy from Waste Plant will face financial penalties from today (January 1).
Infrastructure chiefs want to recoup the cost of handling non-conforming waste after a number of blockages at the Richmond Hill facility.
From now, firms will be charged a handling fee of up to £105 to remove the waste and reload it into their vehicles.
Last year, the site had to be shut down on three separate occasions in the space of a week due to blockages.
Most recently, the plant was taken offline while part of a skip or metal container was removed.
Clearing problems can take up to 48-hours - costing thousands of pounds, as the system is cooled before engineers can access and decontaminate it.
Non-conforming items include; bulky tree trunks and stumps, scaffolding poles, plasterboard, and asbestos.
All users are advised of the changes.
Repeated incidents will result in charges imposed being doubled or tripled.
Port St Mary father continues to fight for change in drug laws
Driving ban for man caught drug driving at the Sea Terminal
'Really important' children are inspired to use their imaginations, says Manx author