Energy expert writes to Tynwald members over Ørsted's project timeline and viability
The chairman of a UK-based energy storage developer has raised concerns about the timeline for grid connection date of the proposed Mooir Vannin Offshore Wind Farm project.
Isle of Man resident Peter Taylor is chairman of The Quarry Battery Company.
He's written to all Tynwald members with concerns about the timeline of Ørsted's project.
An online official record of the grid and connection dates by the National Energy System Operator (NESO) says the proposed offshore Mooir Vannin Wind Farm has a connection date of the 30 September 2037.
However, its status is at Gate 1 - a waiting list - if the company were at Gate 2 this would be a firm connection date.
Ørsted say the project will be operation from 2031-2033 with a possible £2 billion return to the Island over its 35-year operational lifetime.
Mr Taylor has been speaking to Manx Radio's Oliver Sykes:
In response Ørsted told Manx Radio: "We remain confident that the Mooir Vannin can achieve its ambition of generating electricity in the mid-2030s.
"The date within the NESO TEC Register is indicative and should not be confused with a confirmed final or 'earliest' connection date.
"We are engaging directly with NESO and NGET to progress our connection arrangements.
"There remains an opportunity to secure an earlier connection through the Gate 2 process and Mooir Vannin has all the required information in place to submit an application at the next window.
"Grid connections are an evolving area of the UK energy system with significant work underway to accommodate new generation.
"It is not unusual for a firm grid connection to be secured after planning consent is granted."